Below is my timeline:
Aug 3,17 - Filed: I 765, I485, I130 - at NBC based on marriage to a US citizen
Aug 28,17 - Received RFIE asking for tax documents from my sponsor, though I had submitted them
Sep 19,17 - USCIS received response to requestt for evidence
Dec 4,17 - First SR as the case the was beyond normal processing time ( No response yet)
Jan 4,18 - Second SR to received a call back from level 2 officer - On Jan 8, a level 2 officer called back giving no more information than saying that the case is under nomal processing time
Jan 16,18 - Infopass at local field office- the office send an email to NBC via internal system ( No response yet)
Jan 19,18 - Thrid SR to escalate Dec 4th SR- On Feb 16 received response stating that the case is under review and you will receive a decision shorlty
March 16,18 - Card is in production
March 17,18 - We approved your case
March 19, We sent a notice of approval
March 20,18 - We mailed the a card, USPS should deliver it
March 21,18 - The tracker got activitated - I have sign up for USPS informed delivery system. The origin for the card was USCIS- Corbin Production Facility
March 22,18 - Received EAD approval notice in a mail
March 23, 18 - Received physical EAD in a mail
The old USCIS account system -
https://egov.uscis.gov/casestatus/displayLogon.do - does not get updated. The new USCIS account system -
https://myaccount.uscis.dhs.gov/ - gets updated regularly.